in

 

Browse by Tags

  • Re: Actual start/finish and Planned Start/Finish update

    " Daptiv still requires a human to manage the information on some frequency and we have found that this (and baselining) meets the needs of most of our customers compared to an automatically adjusting plan." Do most of your customer have schedules with few tasks and dependencies? Without have...
    Posted to Tasks/Scheduling (Forum) by seaglass on 03-01-2010
  • Re: Limit on number of tasks in a project schedule?

    We have already contacted support, but I was curious if anyone in the user community had experienced an "upper limit" on the number of tasks. With this information, I can better plan for my project managers in developing schedules that conform with the Daptiv environment. Thanks.
    Posted to Tasks/Scheduling (Forum) by seaglass on 07-23-2009
  • Limit on number of tasks in a project schedule?

    Is there any limit to the number of tasks in a project schedule before performance deteriorates? We have had problems with projects containing 800-2000 task items: we have system lockup when deleting tasks and we have problems deleting projects containing this many tasks. We routinely manage schedules...
    Posted to Tasks/Scheduling (Forum) by seaglass on 07-22-2009
  • Fixing Planned Work for Fixed Duration Tasks

    We have been running into this problem for three years and still don't have an answer. Our organization uses Daptiv to track our ongoing work through Support-type projects. Each year, we set up another batch of these and allocate our staff and have them report effort against a small number of tasks...
    Posted to Tasks/Scheduling (Forum) by fladager on 07-08-2009
  • Billable Tasks

    We initially created a project type with "enable external billing" turned off. We later decided that we wanted to utilize external billing, after the entire project schedule was created. Is there any way to go back and make all of the existing tasks "billable" after having enabled...
    Posted to Tasks/Scheduling (Forum) by davidsm on 05-01-2009
  • Does planned start move if predecessor's actual finish is not the planned finish?

    Given these two tasks: Task A plans to start on 12/1 and finish on 12/10 Task B plans to start after Task A finishes (S-F dependency), so planned start is 12/11 (lag=0). If Task A finishes early, it doesn't appear that the planned start for Task B is rescheduled to reflect that work can begin. Is...
    Posted to Tasks/Scheduling (Forum) by Andrew Gross on 11-13-2008
  • Problem with milestones as predecessors

    If milestone "A" is the predecessor to task "B" and task "B" is set to start "as soon as possible" and task B has no other predecessors then task B will be set to start either today or tomorrow...even though milestone A may be scheduled for any number of days out...
    Posted to Projects (Forum) by Andrew Gross on 10-23-2008
  • % Complete values

    Is the % complete displayed in the Project Status pane labeled "Scheduled % Complete" = Effort % complete? Is the % complete displayed on the Projects tab listing labeld [% Complete (Project)] = Duration % complete? Example: Project X - % Complete in the Project Status pane shows 63% Project...
    Posted to Tasks/Scheduling (Forum) by donr on 09-25-2008
Page 1 of 1 (8 items)

Navigate: Home | Blogs | Forums | Solution Library  Get Help:  Contact | Feedback | FAQ   Terms of Use:  Terms & Conditions | Privacy Policy