in

 

ETC Across Entire Project

Last post 06-08-2008 9:47 PM by alloyd. 0 replies.
Page 1 of 1 (1 items)
Sort Posts: Previous Next
  • 06-08-2008 9:47 PM

    • alloyd
    • Not Ranked
    • Joined on 06-08-2008
    • Posts 1

    ETC Across Entire Project

    I need to create a report that shows ETC across an entire project. When I try to use the Cognos reporting tool to do this it is bringing back all the tasks, including parent taks and individual tasks. When I add all these tasks the ETC comes out too high, since a parent task's ETC includes that of all the children, meaning they are double counted. If I could filter a report on whether a task had children or not I could solve this problem but I haven't been able to crack this nut. Anyone have an answer for this?

Page 1 of 1 (1 items)