How to write a report in report builder to pull out timesheet task entries by project???

Last post 04-23-2008 11:47 AM by emarone. 3 replies.
Page 1 of 1 (4 items)
Sort Posts: Previous Next
  • 04-14-2008 9:35 PM

    How to write a report in report builder to pull out timesheet task entries by project???

    Hello,

    Does anyone know how to create a report in report builder that will show me the timesheet entries for each user on each task by project?

    Thanks,

    Tom

  • 04-17-2008 10:00 AM In reply to

    Re: How to write a report in report builder to pull out timesheet task entries by project???

     All Items come from the main Timesheets Folder:

    • Task Work Entry group: Project Name, Work Entry Created On, Hours Worked (and any other desired info)
    • Timesheets group: Timesheet Owner
    • Timesheet Tasks group: Task Name

    Drag them in this order (for easier grouping):

    1. Project Name
    2. Timesheet owner
    3. Task Name
    4. Work Entry Created On
    5. Hours Worked
    6. (any other data at the entry level)

    Group in this order:

    1. Click Projects, Click Group
    2. Click Timesheet Owner, Click Group

     

    What you have left are individul entries, with totals if you pulled in a numeric field.
     

    Steve Thompson | Solutions Consultant
    Daptiv


  • 04-17-2008 5:29 PM In reply to

    Re: How to write a report in report builder to pull out timesheet task entries by project???

    Hi Steve, Thanks for the repy..

     I have created what you have suggested however the Timesheet entry date reflects the date in which they entered in their timesheets and I am after how many hours were recorded and on what day for each task within a project? This is because each resourse may not update their timesheets untill the end of the week or even every 2 weeks.

     I hope this makes sense and I look forward to your responce.

     Many thanks,

    Tom

  • 04-23-2008 11:47 AM In reply to

    • emarone
    • Top 10 Contributor
    • Joined on 09-19-2006
    • Seattle, WA
    • Posts 277

    Re: How to write a report in report builder to pull out timesheet task entries by project???

    The date field you probably want to use is "Work Entry Day" rather than "Work Entry Created On."  Unless I'm mistaken, the Work Entry Day is the calendar day the Task Hours are reported against the task, where Work Entry Created On is the day the work entry was (obviously) created.

    This way, if a Work Entry record for work done on Wednesday the 8th was created at Friday the 10th, the dates should reflect accordingly.  This should break down the work entries by the day the hours were worked rather than the day the work was actually entered in the system.

    Erik Marone | Daptiv Product Manager