in

 

Capacity Plan Numbers Don't Match Resource Allocations

Last post 04-18-2008 1:44 PM by growbot. 2 replies.
Page 1 of 1 (3 items)
Sort Posts: Previous Next
  • 04-10-2008 2:59 PM

    • growbot
    • Top 150 Contributor
    • Joined on 02-29-2008
    • Cupertino, CA
    • Posts 4

    Capacity Plan Numbers Don't Match Resource Allocations

    The numbers entered in the Capacity Planner are not the same as those on the Resource Allocation screen from the projects tab. 

    In the Capacity planner I set one resource type to .5 for 6 months in a row.  In the Resource Allocation window it shows as .48, .48, .5, .48, .5

    I'd like for them to match and generallt don;t understand what is happening here.

  • 04-10-2008 6:35 PM In reply to

    Re: Capacity Plan Numbers Don't Match Resource Allocations

     I assume the enterprise is set to FTE.  Did you submit a support case?  Hours/FTE set in the Resource Planner (Required Hours) should match the Cap Planner.

     

     

    Steve Thompson | Solutions Consultant
    Daptiv


  • 04-18-2008 1:44 PM In reply to

    • growbot
    • Top 150 Contributor
    • Joined on 02-29-2008
    • Cupertino, CA
    • Posts 4

    Re: Capacity Plan Numbers Don't Match Resource Allocations

    Filed a ticket on April 11.  No response yet.