Baselining is only available in Daptiv when the schedule is not checked out, and because Project Transit checks the schedule out as part of the synchronization relationship, it makes this feature unavailable. You could still use the Baseline function of MS Project, but because MSP is technically the schedule "owner" you won't have access to the Daptiv schedule management features.