Project Transit and Baselining Project Plans

Last post 03-31-2008 12:27 PM by emarone. 1 replies.
Page 1 of 1 (2 items)
Sort Posts: Previous Next
  • 03-31-2008 7:10 AM

    Project Transit and Baselining Project Plans

    Is there a way to use project transit and still baseline project plans in Daptiv?  I have not been able to figure out how to do that.  It looks like the two functions are exclusive.  I really like using transit so that I have the power of MS project available to me, but this appears to lock out any ability to baseline in Daptiv.

    Regards,
    Barb Brooks
    Project Manager

    9 Squared
    A Zed Company
  • 03-31-2008 12:27 PM In reply to

    • emarone
    • Top 10 Contributor
    • Joined on 09-19-2006
    • Seattle, WA
    • Posts 283

    Re: Project Transit and Baselining Project Plans

    Baselining is only available in Daptiv when the schedule is not checked out, and because Project Transit checks the schedule out as part of the synchronization relationship, it makes this feature unavailable.  You could still use the Baseline function of MS Project, but because MSP is technically the schedule "owner" you won't have access to the Daptiv schedule management features.

    Erik Marone | Daptiv Product Manager