    Changing task dates

    I have personnel who what to change the dates on tasks, but not the fixed hours. When the dates are changed, the hours are recalculated. Is there a way to prevent the hours from being changed?p>

  • 03-19-2008 1:05 PM In reply to

    Re: Changing task dates

    Set the task type to "Fixed Work" via the edit screen.

    Steve Thompson | Solutions Consultant
    Daptiv