The scheduled hours will show up in the Team Manager and also under the Resource Utilization view in the Resource tab of the project. I have been working with many people to complete the resource management loop without requesting resource. To accomplish this, you can build your team from the enterprise, create your project schedule and assign the resources. Once complete, look at the Resource Utilization view or look at Team Manager for Scheduled hours. Add up the hours for each resource type (a report is perfect for this need) and request those hours for the role. This way, you will see the planned hours and the Capacity Planner will work.
John F. Filicetti, PMP, MBA