You're welcome, glad that did the trick.
Also, I wanted to mention that the way you're using the application isn't "unusual" by any means. The majority of clients I work with do not use Timesheets either, but simply need to track planned/scheduled vs. actual work, exactly as you are. Whether they track by % Complete or ETC generally depends on the relative maturity of their PM processes. ETC is much more precise but requires users and/or managers to assess Task progress at a level many organizations don't yet operate. In my experience, most people who are not seasoned Project Managers tend to think of their work in % complete or % remaining.