Concatenate fields in a view / report

Last post 08-09-2007 2:17 PM by Steve Thompson. 3 replies.
Page 1 of 1 (4 items)
Sort Posts: Previous Next
  • 07-18-2007 4:30 PM

    Concatenate fields in a view / report

    Is it possible to concatenate custom fields added to a project profile on either a view or a report?

     

  • 07-18-2007 4:44 PM In reply to

    Re: Concatenate fields in a view / report

    You can use the field type of Calculate.  Chose Concatenate as the type of calculation and then select the fields you want to use.  You can also type in other characters, so if you want a "-" between City and State, the formula would be City-State.

    John F. Filicetti, PMP, MBA
  • 07-18-2007 5:18 PM In reply to

    Re: Concatenate fields in a view / report

    John -

    Great!  So the new field is now available to pull into views/reports.  Is there a way to "suppress" or hide the fields at the project profile level that were used to create the new field so that only the concatenated field is visible? 

  • 08-09-2007 2:17 PM In reply to

    Re: Concatenate fields in a view / report

    Currently, no.  It is on our road map to make selected fields hidden or visible.
    Steve Thompson | Solutions Consultant
    Daptiv