Hi Steve,
Thanks for your reply. I went back in and played around but including the Incremental Work value doesn't do what I need either. For one thing, it removes from the table tasks that have no work (something I don't want to have happen) and second, it seems to present values that don't make sense. For example, a task has a total planned work of 408 and a total actual work of 1.25 (which I can verify by going into and viewing the tast updates). Then there is an Actual Work Hours value of 5.00 and an Incremental Work of 18.25.
I pulling the Project Name, the WEB, Task Name, % Complete, Start, Finish, the fields I mentioned above, ETC, and Resource Full Name. If I could post a screenshot, I would.
Thanks!
Darlene