Thanks Steve, but that unfortunately does not remedy it. I do, however, use the "-1" lead time to another task to make sure "B" doesn't start too early, i.e. task "AA" below.
So what I have setup is
Task "AA"
Milestone "A"
Task "B"
Milestone "A" has task "AA" as a predecessor". I wanted to link task "B" to "A" per the first post. But since this doesn't work, I link "B" to "AA". When "B" is linked to "A", A's finish date is ignored.
AEG