    Problem with milestones as predecessors

    If milestone "A" is the predecessor to task "B" and task "B" is set to start "as soon as possible" and task B has no other predecessors then task B will be set to start either today or tomorrow...even though milestone A may be scheduled for any number of days out.  Looks like a bug to me. 

    Anyone come up with a workaround?

     

  • 10-23-2008 1:49 PM In reply to

    Re: Problem with milestones as predecessors

     Set a lead in time of -1.  Try that.

    Steve Thompson | Solutions Consultant
    Daptiv


  • 10-23-2008 1:57 PM In reply to

    Re: Problem with milestones as predecessors

    Thanks Steve, but that unfortunately does not remedy it.  I do, however, use the "-1" lead time to another task to make sure "B" doesn't start too early, i.e. task "AA" below.

     So what I have setup is

    Task "AA" 

     Milestone "A"

    Task "B"

     Milestone "A" has task "AA" as a predecessor".  I wanted to link task "B" to "A" per the first post.  But since this doesn't work, I link "B" to "AA".  When "B" is linked to "A", A's finish date is ignored.

     

    AEG