in

 

The logic for Task Status udpates

Last post 09-02-2008 11:29 PM by Steve Thompson. 1 replies.
Page 1 of 1 (2 items)
Sort Posts: Previous Next
  • 09-02-2008 10:21 PM

    • matilda
    • Top 75 Contributor
    • Joined on 11-14-2007
    • Brisbane, Australia
    • Posts 11

    The logic for Task Status udpates

    Is there a document or help page on the logic daptiv uses when automatically updating a Task Status i.e. the triggers and the work flows of each Status? I was unable to find on community pages. Additionally is there anywhere an Administrator can override this logic similar to the Project Health automatic updates?

    The reason I ask is that we are wanting a report that breaks down Tasks into categories Not Started; Not started and overdue; In Progress and started Late; In Progess and started on time; In Progress and started early; Completed and finished early, Completed and finished on time.. etc and the Task Status field cant be fully relied upon for our purpose.

    Some examples

    - If a Task has a status of 'Overdue' putting an actual start date on it, even when it is the same as the planned start, does not update it back to In Progress. Once Overdue it can only move to Completed?

    - If a task is Status 'On Hold' , putting an actual start date on it, one that is after the planned start, does not change the Task to 'In Progess'. Once On Hold can you only change a Task to 'In Progress' by using the 'Checked Item Actions' (such as 'Mark as In Progress(50% )' )?

    - If a task is On Hold and I give it an actual finish date (even if I put a future date), daptiv updates it to Completed status, it seems Completed over-rules On Hold and it doesn’t care if the task isnt actually yet completed (finish date yet to occur). In this case it could be argued that it is still In Progress (as finish date in future)?

     thanks

     

  • 09-02-2008 11:29 PM In reply to

    Re: The logic for Task Status udpates

    For your reports you will want to use conditional formatting for Planned Start, Actual Start and Current Date.  The Status field isn't going to give you the detailed breakdown of your requirements.  You will create a calculated status field on your report that represents the color/textual status of your requirements based on your conditions, rather than use the native Task Status field.

     Task Status logic can not be modified other than placing a task on hold.  Other than that it is driven by dates and % complete.

     

    matilda:

    - If a Task has a status of 'Overdue' putting an actual start date on it, even when it is the same as the planned start, does not update it back to In Progress. Once Overdue it can only move to Completed?

    No, a task is overdue so long as today's date is beyond the planned finish and % complete is less than 100.

    matilda:

    - If a task is Status 'On Hold' , putting an actual start date on it, one that is after the planned start, does not change the Task to 'In Progess'. Once On Hold can you only change a Task to 'In Progress' by using the 'Checked Item Actions' (such as 'Mark as In Progress(50% )' )?

    Percent or hours indicate that work is being done, or Actual Finish (indicating 100%).  Start date does not drive these elements.

     

    matilda:

    If a task is On Hold and I give it an actual finish date (even if I put a future date), daptiv updates it to Completed status, it seems Completed over-rules On Hold and it doesn’t care if the task isnt actually yet completed (finish date yet to occur). In this case it could be argued that it is still In Progress (as finish date in future)?

    I suppose our Finish Date is a dummy field in respect to the current date, and that if there is a date entered, the logic considers the task to be finished (since that's the whole point of Actual Finish).  Otherwise you effectively have 2 planned finish dates in your scenario.

     

     

    Steve Thompson | Solutions Consultant