Steve,
Here's an example of this from the reporting standpoint.
I have a report (the Director's Portfolio) that list projects and programs. When a program is listed and the separate projects are included under it, the planned finish date and scheduled finish date of the program don't seem to come from the component projects.
Project # Project Name PM Phase PlannedStart ScheduledStart PlannedFinish ScheduledFinish
135 Stellar CMS D. J. Execute 1/31/08 1/31/08 8/31/08 8/31/08
102 Stellar 2.2 D.J. Execute 2/15/08 3/3/08 8/15/08 8/29/08
150 Stellar 3.0 D.J. Execute 2/15/08 2/15/08 7/15/09 7/15/09
Note that the first project is the overall program for the second 2 and does not have any tasks.
Why wouldn't the Planned Finish date (entered through the Project Profile) for the 2 projects cause the Planned Finish date of the program to change. Same thing for the Scheduled Finish dates (taken from the latest scheduled tasks for the 2 projects)?
Thanks!
Darlene