  • 05-14-2008 11:46 PM

    Cross Dependent Tasks

    Has anyone found a workaround to have the cross project dependent tasks auto update in the other projects?  I've created "milestone" in projects that are a cross dependency to tasks in other projects - but they do not auto update when the originating project date moves.  I know about scheduling work flow notification, etc. and the ghantt chart alert - but I have 13 projects interelated and am looking for an auto method.

     

    thank you

  • 05-15-2008 8:42 AM In reply to

    • emarone
    • Top 10 Contributor
    • Joined on 09-19-2006
    • Seattle, WA
    • Posts 270

    Re: Cross Dependent Tasks

    Currently, cross-project dependencies only give a visual indicator in the Gantt chart when the upstream task compromises the successor.  However, this kind of automatic schedule adjustment capability is something we are evaluating for the scheduling engine enhancements we will be undertaking in the near future.

    Erik Marone | Daptiv Product Manager