    Sequential Tasks in One Day

    I have a project manager with a plan with multiple small tasks (<1 hour). When he uploaded the plan, these tasks moved to different days, rather than scheduling them all on the same day (even with multiple resources assigned). Is this by design, or is there some property we're overlooking that will allow us to schedule them on the same day?

     Thanks,

    Karen

    Karen
  • 01-17-2008 4:12 PM In reply to

    Re: Sequential Tasks in One Day

    Daptiv Tasks have a minumum Duration of 1 day so if you have a series of 1 day tasks with FS predecessor relationships, then it is not possible to have them occur on the same day.  

    To set them up properly in Daptiv's Gantt, edit your dependency and set a lead time of "-1".  This will put them all to occur on the same day.

    It is in our roadmap in Gantt 2.0 to revise our engine to support less than one day duration.

     

    gantt tasks with deps.

     


    Steve Thompson | Solutions Consultant
    Daptiv