So we have been using eProject for a while but are just now looking to tackle using transit. We are still learning through several pilot projects with lots of questions and concerns. One of the most significant is how actual work is being reported.
During sync, you see that actual work in ms project is not mapped to anything in eproject. this does not seem like how it actually works though as in most cases, but not all for some reason, eproject does in fact update actual work in ms project based on time booked in eproject. what we don't understand is why does it sometimes work and in some cases is does not. along the same lines, it seems like transit maps actual % complete (based on time logging) to % complete in ms project and not % work complete.
Has anyone figured this out? Specifically the relationships between ms project and eproject for % complete and actual work.
my thanks in advance for your assistance...