    for example, how can I make task #1 into task #8?  I know I can change sort order (e.g. by start date, by end date, etc) but I actually want taskj #1 to be come task #8, and current task 2-7 move up one.

  • 11-15-2007 4:17 PM In reply to

    Re: how to re-order tasks

     There are a few ways to do this.

    To reorder your tasks, edit the task you want to move and midway down the edit form is a "Move After" pick list.  Select the task you want to move it after and it will reorder them accordingly.  You may also reorder tasks from the Gantt by draging a task (or multiple tasks) by clicking (ctrl clicking) on the TASK NUMBER on the left, then drag above the TASK NAME in the list that you want to move them above.  The icon will change to let you know when to drop.

     

     

    Steve Thompson | Solutions Consultant
    Daptiv


Page 1 of 1 (2 items)

Navigate: Home | Blogs | Forums | Solution Library  Get Help:  Contact | Feedback | FAQ   Terms of Use:  Terms & Conditions | Privacy Policy